CUXHAVEN. Work on the Alte Liebe began in calendar week 48 of 2026. The new structures for this Cuxhaven landmark are being built using timber construction methods. This involves installing around 35 cubic metres of load-bearing timber framework and approximately 700 square metres of weather-resistant timber planking. Finally, the railings, staircases, timber walls and cladding will be fitted, along with the harbour equipment and electrical works. The new structure will be around 55 metres long and 8.60 metres wide. The refurbished viewing platform is to be positioned around one metre higher than before in order to meet the increased requirements for storm surge protection. Access will be designed to be barrier-free. The Alte Liebe will remain closed to visitors during the construction period. Completion is scheduled for the third quarter of 2027.
Photo: Andreas Burmann, NPorts